Manufacturing of Split Flange for TITIAN for BP Tangguh Turnaround Project

LIMOV just delivered Split Flange to PT Titian Servis Indonesia. It will be used in BP Tangguh Piping Turnaround 2024. The Split Flange is one of the most critical part and the final touch in the piping system.

Design and construction of Service Crane for Pertamina Algeria Compressor Turnaround Project

On June 2023, Pertamina Algeria together with Sonatrach shutdown the Menzel Ledjmet Nord oil field in Algeria in order to replace the Bundle Compressor. The compressor building was not designed for this kind of job because it does not have service crane or any other handling system for the bundle replacement job. The compressor is …

Engineering and construction of Service Crane for Pertamina Algeria MLN H-101 Fired-Heater Radiant Coil Turnaround

Together with Pertamina Algeria and Sonatrach team, LIMOV completed the Radiant Coil replacement for H-101 Fired Heater in Menzel Ledjmet Nord (MLN) Oil Field, Algeria. It is the most critical job during the scheduled MLN 2020 Turnaround. The method of building modular tower crane inside the Fired Heater to extract all the old pipe bundles …

LIMOV and Pertamina Algeria perform trial of LIMOV Service Crane for H-101 Radiant Coil Replacement in MLN Oilfield

We are doing shop assembly and trial for the LIMOV Tower Crane which was designed and built for Radiant Coil Replacement. The trial is performed in Sahara Desert in Menzel Ledjmet Nord (MLN) Oilfield, Algeria. After the trial and inspection, the pipe handling system will be dismantled and rebuild again inside H-101 Fired Heater in …